Brokenhead Wetland Interpretive Trail Design

Design prepared 2006-Jan03 by:

TD09-Hilderman-Logo

Funding provided by: Brokenhead Ojibway Nation, and Manitoba Model Forest

Presentation prepared 2006-Oct by Eugene Reimer

Since 2003, there has been an informal committee to plan for the protection and future management of the Brokenhead Wetland area.  Doris and I have been on it representing NOCI; other NOCI directors like Richard & John have also attended some meetings.  The Brokenhead Ojibway Nation has been playing the lead role, including chairperson Carl Smith, elder Lawrence Smith, councillors Bev Smith and Paul Chief.  It also includes Rene Barker from the Hollow Water first-nation, Kelly-Ann Richmond from the Manitoba Protected Areas Initiative, and (did include) Mike Waldram of the Manitoba Model Forest organization.

After this area received Ecological Reserve status in June of 2005, this committee has been focusing on getting a Boardwalk and Interpretive Trail built.  Having a boardwalk in the wet areas will help to protect the sensitive habitat.  It will also protect the visitors, preventing them from sinking and vanishing in the bog (smile).

TD01-09161-Boardroom-RobNedotiafko_2005oct25_erCB420

01: here’s part of that committee, at a meeting chaired by Rob Nedotiafko of the landscape architecture firm Hilderman Thomas Frank Cram.  Incidentally, the Brokenhead Ojibway Nation and Manitoba Model Forest provided the money (approximately $15,000) to pay for the design work done by that firm.  Both Mike Waldram and Carl Smith had a lot to do with arranging this funding.

TD02-09158-Boardroom-Carl_2005oct25_erCB420

02: the same meeting – from the other end of the room.

TD03-09109-Trailwalk_2005sep15_erCCB420
03: In 2005-September, Carl and Doris and I walked the trail with a GPS in order to “map” it.  This is a pleasant spot where we paused for a break.

TD04-09165-Trailwalk_2005oct25_erCB420

04: In 2005-October, we did another more thorough mapping trailwalk.  This time the 3 young fellows from the architecture firm used maps as well as GPS’s to make sure everything was done correctly and that we stayed within the 100-metre-wide strip.

TD05-09170-Trailwalk_2005oct25_erCOMPOSITE-CAAA420

05: This is that group at the south end of the proposed trail, where we finished; we were a weary bunch – at least I was.

TD06-Drawing-L1-TrailMap_C990

L1-Map: Note Hwy 59, and the curve where we have been stopping and entering the area on fieldtrips in the past, from the south end.  Our new proposed design needs a parking lot, and the Highways Dept would never dream of allowing that sort of “intersection” in the middle of a curve.  Access from the south end is out of the question for many reasons.

Incidentally, the Eco-Reserve is the western portion of this map, also extending further to the west (it’s 560 hectares, or three times the size of Assiniboine Park); everything to the east, til PTH59, had a gravel-lease owned by Riverside Gravel; however they’ve given up the 100-metre-wide strip, outlined in red, which contains exactly those highlights that we’ve been featuring on fieldtrips.

At the north end, on a municipal road-allowance, is the proposed entrance and parking-lot, and where the trail will start.  This first part is mostly dry – the Yellow parts of the trail are where we plan to construct a gravel path (at a much lower cost per metre).  The Blue parts are the proposed boardwalk.  The Green parts are also boardwalks – but these are Optional (later I’ll show Cost-Estimates both with and without these Optional Boardwalk parts.)

TD06-Drawing-L2-ParkingAreaPlan_C800

L2-Parking-Area: The parking lot fits entirely within a 99-foot (one and a half chain) road-allowance, has room for about 20 cars plus a few buses, and the U-shaped part allows a long bus to turn around.

TD06-Drawing-L31-GranularPavementDetails_C800

L3.1-Granular-Details: The parking lot will get granular base to 12-inch depth; the gravel trail to 4-inch depth.

TD06-Drawing-L32-BollardDetails_C800
L3.2-Removable-Bollard: This bollard is to prevent access by motorized vehicles; it is removed when maintenance personnel need to use such vehicles.

TD06-Drawing-L41-FramingPlan_C800
L4.1-Framing-Plan: The framing is much like the floor of a house, using 2×10 joists, with 16inch spacing (approximately).  (The next few slides will show what the joists sit on, and will better illustrate the railings and curbs.)

We have looked at 3 different materials for the 2×6 decking:
TREX (which is made from a mixture of recycled plastic bags and wood waste), or
Cedar, or
Pressure-treated wood. 

For the structural parts we’ve only considered 2 materials:
Douglas Fir, or
Pressure-treated wood. 

TD06-Drawing-L42-BoardwalkSection_C800
L4.2-Boardwalk-X-section: The x-section view.  The foundation involves 3 and 1/2 inch outside-diameter galvanized-steel posts, which go through the wet peat and at least 3 feet into the more solid ground below.  Each pair of posts is tied together with a galvanized-steel beam and U-bolts; the joists rest upon those beams.

TD06-Drawing-L43-RailingSection_C800
L4.3-Railing-section: Another x-section view, showing the railing and curb details.  The railing uprights are attached with carriage-bolts.  Wherever the boardwalk is so high that stepping off could be hazardous, we’ll have such a railing; where it’s not so high, we’ll have just a curb.

TD06-Drawing-L44-NodeFramingPlan_C800
L4.4-Node-plan: Our plan calls for 3 of these “resting-point nodes” situated at places where people might wish to linger.  Such a node is built in much the same way as the boardwalk.

Table 1: Budget Estimate (Class C ±15%)

    Quantity   Unit-Price Amount
A. Preliminary Site Development
Parking Lot, Approach & Access Road
Clearing & Grubbing 3000 sq.m $3.00 $9,000.00
Rough Grading 3000 sq.m $3.00 $9,000.00
Gravel Trail
Clearing & Grubbing 1000 sq.m $3.00 $3,000.00
Peat Stripping (assume 100mm depth avg) 100 cu.m $5.00 $500.00
Rough Grading 1000 sq.m $3.00 $3,000.00
Boardwalk – Tree Clearing by hand
Main Boardwalk 1 allow $5,000.00 $5,000.00
Optional Boardwalk 650m 1 allow $2,500.00 $2,500.00
Contingency 15% $4,800.00

TOTAL $36,800.00
B. Finish Surface Development
Gravel Parking Lot & Approach 900 cu.m $30.00 $27,000.00
(300mm Depth Granular Base)
Gravel Trail Surface 800 sq.m $10.00 $8,000.00
(1/4″ down; 1.8m width; 100mm depth base)
Contingency 15% $5,250.00

TOTAL $40,250.00
C. Boardwalk Construction Options:
Option 1: Pressure Treated Wood (ACQ) for Structure, Decking & Railing
Main Boardwalk – Posts, structure & Decking
6′ Width 100% length 1100 l.m. $352.00 $387,200.00
Railing – on both sides for 50% length 550 l.m. $127.00 $69,850.00
Curb – on both sides 50% length 550 l.m. $25.00 $13,750.00
Contingency 15% $70,620.00

TOTAL $541,420.00
Optional Boardwalk
6′ Width 100% length 525 l.m. $352.00 $184,800.00
Railing – on both sides for 40% length 210 l.m. $127.00 $26,670.00
Curb – on both sides 20% length 105 l.m. $25.00 $2,625.00
Contingency 15% $32,114.25

TOTAL $246,209.25
Resting Points
Node 3 each $825.00 $2,475.00
Contingency 15% $371.25

TOTAL $2,846.25
OPTION 1 TOTAL $790,475.50
Option 2: Douglas Fir Structure with Cedar Decking and Railing
Main Boardwalk – Posts, structure & Decking
6′ Width 100% length 1100 l.m. $380.00 $418,000.00
Railing – on both sides for 50% length 550 l.m. $108.00 $59,400.00
Curb – on both sides 50% length 550 l.m. $30.00 $16,500.00
Contingency 15% $74,085.00

TOTAL $567,985.00
Optional Boardwalk
6′ Width 100% length 525 l.m. $380.00 $199,500.00
Railing – on both sides for 40% length 210 l.m. $108.00 $22,680.00
Curb – on both sides 20% length 105 l.m. $30.00 $3,150.00
Contingency 15% $33,799.50

TOTAL $259,129.50
Resting Points
Node 3 each $915.00 $2,745.00
Contingency 15% $411.75

TOTAL $3,156.75
OPTION 2 TOTAL $830,271.25
Option 3: Pressure Treated (ACQ) Structure with TREX Decking & Railing
Main Boardwalk – Posts, structure & Decking
6′ Width 100% length 1100 l.m. $503.00 $553,300.00
Railing – on both sides for 50% length 550 l.m. $242.00 $133,100.00
Curb – on both sides 50% length 550 l.m. $62.00 $34,100.00
Contingency 15% $108,075.00

TOTAL $828,575.00
Optional Boardwalk
6′ Width 100% length 525 l.m. $503.00 $264,075.00
Railing – on both sides for 40% length 210 l.m. $242.00 $50,820.00
Curb – on both sides 20% length 105 l.m. $62.00 $6,510.00
Contingency 15% $48,210.75

TOTAL $369,615.75
Resting Points
Node 3 each $1,120.00 $3,360.00
Contingency 15% $504.00

TOTAL $3,864.00
OPTION 3 TOTAL $1,202,054.75
D. Optional Site Developments
Signage 1 allow $10,000 $10,000.00
Site Furnishings 1 allow $10,000 $10,000.00
Latrines (removable) 2 each $1,500 $3,000.00
Observation Tower – Steel Frame 1 allow $100,000 $100,000.00
Picnic Shelter – 25’x25′ 1 allow $31,250 $31,250.00
Contingency 15% $23,137.50

OPTIONAL SITE DEVELOPMENTS TOTAL $177,387.50

Table 2: Budget Estimate SUMMARY (Class C ±15%)

Basic Trail With
Optional
Part
OPTION 1: ALL PRESSURE TREATED WOOD (ACQ)
A. Preliminary Site Development $33,925 $36,800
B. Finish Surface Development $40,250 $40,250
C. Boardwalk Option 1 $544,266 $790,476


TOTAL: $618,441 $867,526
OPTION 2: DOUGLAS FIR STRUCTURE & CEDAR DECKING
A. Preliminary Site Development $33,925 $36,800
B. Finish Surface Development $40,250 $40,250
C. Boardwalk Option 2 $571,142 $830,271


TOTAL: $645,317 $907,321
OPTION 3: PRESSURE TREATED STRUCTURE & TREX DECKING
A. Preliminary Site Development $33,925 $36,800
B. Finish Surface Development $40,250 $40,250
C. Boardwalk Option 3 $832,439 $1,202,055


TOTAL: $906,614 $1,279,105

Note that Table-2 provides six different “bottom lines”, broken down by the boardwalk-material choice, and by whether or not we build the Optional Parts of the boardwalk.  They range in price from roughly $600,000 to well over a million dollars.  (None of these include any of the “Part D Optional Site Developments”, which can add up to another $200,000 to any of these pricetags.)
Next Steps:

(i) We see the need to replace our informal committee with a more formal organization – one that is incorporated, and has charity status so it can give donors tax-deductible donation-receipts.  It will look after fund-raising, taking care of the trail during construction, and over its lifetime.  Debwendon Inc (Debwendon is an Ojibway word meaning “trust”) will be that organization.  [As of 2009-January, Debwendon Inc exists and has charity status.]

(ii) We intend to prepare a professional video presentation to present to potential funders.  [As of 2008-January, the video has been completed and can be seen at  EKO video  on Debwendon.Org.]
Conclusion:
NOCI has pledged $12,500 toward the construction of this trail; so it only needs another $606,000.